Upcoming Road Work for Mid-Missouri May 4-13

The following is a listing of general highway maintenance and construction work in the mid-Missouri area for May 4 - May 13. Weather conditions may cause postponements in the work schedule.

Other construction or maintenance work may occur on other roadways throughout the area. Many projects will include lane closures and delays can be expected.

MoDOT reminds the public to buckle up, slow down, follow posted signing and drive safely through work areas. For more information about a project, please contact MoDOT at 1-888-ASK-MoDOT (275-6636) or log onto www.modot.org/central.

Benton County

Daylight Hours

Route 65 from south of Route 52 to just north of the Osage River in Warsaw

- Widening highway to four lanes continues. The contractor continues

working on grading, culverts and pipe work, and roadway construction.

Traffic on existing Route 65 is not affected.

The project is scheduled to be complete in summer 2012.

Route 7 bridge west of Route UU - Bridge maintenance will take place

Wednesday, May 4 and Thursday, May 5. One lane will be open and crews will

flag traffic through the work area.

Route P between Route E and Route ZZ - Partial paving and roadway repair

continues through Thursday, May 5. One lane will be open and crews will

flag traffic through the work area.

Boone County

Daylight Hours

Interstate 70 between the Missouri River Bridge and Route BB - Concrete

barriers are in place on the eastbound shoulder. Crews are working in the

shoulder area to excavate and repair a portion of roadside fill to prevent

the soil from sliding and damaging the pavement. Both eastbound lanes are

open to traffic during the work. The ramp to Route BB is narrowed. The work

continues through late July.

Daylight/Overnight Hours

Interstate 70 Northeast Outer Road bridge over Little Cedar Creek, one mile

east of Route Z - Bridge replacement continues. The bridge is closed to

traffic until early June. Motorists should seek alternate routes around

the work. This is part of the Safe & Sound Bridge Improvement Program.

Interstate 70 bridge over Hominy Creek at mile marker 130 - Bridge

maintenance and repair in the westbound lanes will take place on Monday,

May 9. One westbound lane will be open through the work area.

Interstate 70 bridge over Route 763 - Bridge maintenance and repair in the

westbound lanes will take place on Tuesday, May 10 One westbound lane will

be open through the work area.

Interstate 70 bridge over Garth Avenue - Bridge maintenance and repair in

the westbound lanes will take place on Wednesday, May 11. One northbound

lane will be open through the work area.

Route WW bridge over Route 63- Bridge maintenance and repair will take

place on Thursday, May 12. One lane will be open and crews will flag

traffic through the work area.

Callaway County

Daylight Hours

Route A, just north of Route B - Culvert pipe replacement will take place

on Wednesday, May 4. The route will close to traffic at 7:30 a.m. for

approximately six hours. Motorists should seek alternate routes around the

work area.

Route K between Route D and the Montgomery County line - Roadway paving

will take place on Friday, May 6. One lane will be open and crews will flag

traffic through the work area.

Route BB between Route 54 and Route AA

Route MM between Route J and end of state maintenance - Partial surface

overlay continues through Friday, May 6. One lane will be open and crew

will flag traffic through the work areas.

Route PP, 1.5 miles north of Route 94 - Roadway maintenance and repair will

take place on Thursday, May 5. One lane will be open and crews will flag

traffic through the work area.

Daylight/Overnight Hours

Route 63 near over Cedar Creek, 1.5 miles south of the Boone/Callaway

County line -Bridge deck replacement and upgrading guard rail in the

northbound lanes.

  • The northbound bridge is closed traffic during until late May. During

this time, northbound traffic will be redirected onto one southbound lane

for approximately ? mile.

  • Bridge painting will take place after the bridge reopens, but some

lane closures may still be needed to finish that work.

This project is part of the Safe & Sound Bridge Improvement Program.

Camden County

Daylight Hours

Route 54 in Linn Creek at the intersections of Route V and Business Park

Road/East Valley Drive - Median turn lane construction and intersection

improvements. Grading and asphalt work continues for the new Business Park

Road and East Valley Drive widening.

  • One lane in each direction will be closed periodically in the work

area for the next few weeks as crews grade near offset turn lanes.

Motorists should expect delays.

This project is scheduled for completion in late spring 2011.

Route 5 bridge over the Osage Arm of the Lake of the Ozarks - Routine

bridge inspection is scheduled during the week of May 2. One lane will be

open through the work area.

Route 5 South between Route 54 and Route 7 - Bridge maintenance continues

through Wednesday, May 4. One lane will be open and crews will flag

traffic through the work area.

Daylight/Overnight Hours

Route 54 between the Grand Glaize Bridge to west of Route KK in Osage Beach

- Grading, drainage work, paving and bridges for the new Route 54

Expressway.

  • Traffic on Laguna Beach Road is routed on the service road where they

will access the new Case Road Interchange.

  • Grading continues from Laguna Beach Road to the Grand Glaize Bridge.

  • The contractor is placing rock base on the new Route 54 Expressway

from Route KK to the west end of the project.

  • The contractor is building the new Route KK bridge while traffic is

using existing Route KK.

  • Work continues on the new Nichols Road. Minor traffic delays can be

expected as construction equipment accesses these areas. The New Nichols

Road is tentatively scheduled to open to traffic the week of May 9.

  • Key Largo Road traffic has moved to their new location west of where

they currently access existing Route 54.

This portion of the project is scheduled for completion in summer 2011.

Route W bridge over Watson Creek, approximately 3.5 miles west of Route 54

- Bridge replacement continues. The bridge is located 3.5 miles west of

U.S. 54. The bridge is closed to traffic through late May. Motorists

should seek alternate routes around the work area. This project is part of

the Safe & Sound Bridge Improvement Program.

Camden and Miller Counties

Daylight Hours

Route 242/Horseshoe Bend Parkway between Lake Ozark Community Bridge and

Route 54 - Grading and paving for a new four-lane highway.

  • The contractor is excavating and placing material on the western end

of the project near the Community Bridge.

  • Drainage pipe is being placed near the west end of the project and

construction is underway on a box culvert farther east in the work area.

No traffic delays expected at this time.

This project is scheduled for completion in late winter 2011.

Cole County

Daylight Hours

Route 50/63 between Militia Drive and City View Drive - Pavement repair in

the westbound lanes continues through Wednesday, May 4. One westbound lane

will be open to traffic through the work area.

Route 179 between Route N and the Jefferson City limits - Roadway

resurfacing continues through Friday, May 13. One lane will be open and

crews will flag traffic through the work area.

Route B bridge over the Osage River, approximately 2.5 miles south of Route

E - Bridge maintenance and repair will take place Tuesday, May 10 through

Thursday, May 12. One lane will be open and crews will flag traffic

through the work area.

Route C bridge over the Moreau River, 3.5 miles east of Route D - Bridge

maintenance and repair will take place on Wednesday, May 4. One lane will

be open and crews will flag traffic through the work area.

Route T from just north of Route 50 to Route 179 - Partial surface overlay

will take place Monday, May 9 through Friday, May 13. One lane will be

open and crews will flag traffic through the work area.

Cooper County

Daylight Hours

Route W between Route J and end of state maintenance - Partial paving and

repair will take place on Thursday, May 5. One lane will be open and crews

will flag traffic through the work area.

Route EE between Route 87 and Route 179 - Partial paving and repair will

take place on Wednesday, May 4. One lane will be open and crews will flag

traffic through the work area.

Daylight/Overnight Hours

Route V bridge over the Petite Saline Creek, approximately two miles south

of Route 179 - Bridge replacement is nearing completion. The bridge is

tentatively scheduled to open to traffic the week of May 2. This project is

part of the Safe & Sound Bridge Improvement Program.

Gasconade County

Daylight Hours

Route 100 between Route 19 and Route N - Partial surface overlay continues

through Thursday, May 12. One lane will be open and crews will flag

traffic through the work area.

Route B, 4.5 miles south of Route 28 - Culvert pipe replacement will take

place on Thursday, May 5. One lane will be open and crews will flag

traffic through the work area.

Maries County

Daylight Hours

Route 42 between Route 63 and the Miller County line - Partial surface

overlay continues through Thursday, May 12. One lane will be open and

crews will flag traffic through the work area.

Miller County

Daylight Hours

Route CC between Route 52 and the Moniteau County line - Culvert pipe

replacement in various locations continues through Thursday, May 5. One

lane will be open and crews will flag traffic through each work area.

Route 87 between Business Route 54 and the Moniteau County line and

Route Y between Route 52 and the Morgan County line - Partial surface

overlay will take place Tuesday, May 10 through Thursday, May 12. One lane

will be open and crews will flag traffic through each work area.

Moniteau County

Daylight Hours

Route D between Route O and Route U - Partial paving and repair will take

place on Friday, May 6. One lane will be open and crews will flag traffic

through the work area.

Route MM between Route F and end of state maintenance - Partial paving and

repair continues through Friday, May 6. One lane will be open and crews

will flag traffic through the work area.

Daylight/Overnight Hours

Route E bridge over Dry Fork, one mile south of Route 50 - Bridge

replacement continues. The bridge is closed to traffic until mid-May.

Motorists should seek alternate routes. This project is part of the Safe &

Sound Bridge Improvement Program.

Morgan County

Daylight Hours

Route W between Route AA and Versailles city limits - Partial surface

overlay continues through Wednesday, May 4. One lane will be open and

crews will flag traffic through the work area.

Osage County

Daylight Hours

Route Z between Route 100 and end of state maintenance - Roadway

maintenance and repair will take place Wednesday, May 4 and Thursday, May

  1. One lane will be open and crews will flag traffic through the work

area.

Pettis County

Daylight Hours

Route 65 between Route 52 and Sedalia city limits - Concrete replacement in

the northbound and southbound lanes continues through Friday, May 6. One

lane in each direction will be open to traffic through the work area.

Route 65 bridge over Turkey Creek, north of Smelser Road and

Route 65 bridge over Muddy Creek, north of John Road - Bridge maintenance

and repair in the northbound lanes continues through Wednesday, May 4. One

northbound lane will be open through each work area.

Daylight/Overnight Hours

Route V bridge over Spring Fork Creek, east of Route 65 - Bridge

replacement continues. The bridge is nearing completion. The bridge is

tentatively scheduled to open to traffic on Thursday, May 5. This project

is part of the Safe & Sound Bridge Improvement Program.

Route HH bridge over Cedar Creek, four miles east of Route 65 - Bridge

replacement is scheduled to begin on Monday, May 2. The bridge will be

closed to traffic until mid-June. Motorists will be detoured around the

work area on U.S. 65, Route 50 and Route O. This project is part of the

Safe & Sound Bridge Improvement Program.

Pettis, Morgan and Moniteau Counties

Daylight Hours

Route 50 from east of Sedalia city limits to Tipton city limits - Roadway

resurfacing continues in driving lanes and shoulders through early fall of

  1. One lane will be open and crews will flag traffic through the work

area.

MoDOT encourages motorists to log onto www.modot.org/central to comment on

their experiences traveling through highway work zones.