• U.S. 54 between Old Bass Road and Route CC - Improvements at 12 intersections along 8.5 miles of U.S. 54 to improve safety and traffic flow.

  • Most work on the project is suspended for the winter, but crews will be working off the roadway at Buffalo Road and installing lighting in various locations. Work to install lighting will take place on the shoulder of the roadway.

The entire corridor is scheduled for completion in the fall.

• Missouri 179 between Route C and Edgewood Drive - Grading, drainage, and bridge paving for a new interchange. Periodic lane closures may occur, and motorists are advised to use caution through the area. The entire project is scheduled for completion in the summer.

Cole, Moniteau and Morgan counties

• U.S. 50 between Jefferson City and the Pettis County line - Roadway striping will take place this week. One lane will be open to traffic through the work area. This is a moving operation, and motorists should drive with care through the area.

Boone County

• U.S. 63 from just north of Missouri 163 to Route H - Construction of a new diamond interchange and southbound lanes. Motorists should expect periodic lane closures.

  • Route H is temporarily closed at 63. Traffic is being detoured to Hardwick Lane, located near the 63 roadside park. Route H will remain closed at 63 until the new interchange opens to traffic.

  • The contractor continues with bridge construction at Turkey Creek and at H.

  • Motorists should be prepared for periodic reductions in speed limits through the work area. The entire project is scheduled for completion late this year.

• Route PP between U.S. 63 and the end of state maintenance - Culvert pipe replacement in various locations will take place Monday through Wednesday. One lane will be open, and crews will flag traffic through the work area.

Callaway County

• Route J north of Route Y - Culvert pipe replacement will take place Wednesday. One lane will be open, and crews will flag traffic through the work area.

Camden County

• U.S. 54 at the Missouri 5 interchange in Camdenton - Sidewalk construction and ramp widening is under way.

  • Traffic has been shifted to accommodate the installation of temporary barrier curbs in preparation for sidewalk construction across the U.S. 54 overpass bridge.

  • Motorists should expect lane closures and the narrowing of U.S. 54 traffic lanes through the interchange area during construction. Minor delays are possible.

The entire project is scheduled for completion in mid-May.

Maries County

• Missouri 28 bridge over Dry Fork two miles south of Route Z - Bridge replacement is under way.

  • The bridge is closed to traffic through early April. Motorists are being detoured around the work area on Routes 63, 42 and Z.

  • The weight limits on the Route C bridge over Peavine Creek have been upgraded for truck usage. This project is part of the Safe & Sound Bridge Improvement Program.

• Route BB bridge over the Little Maries River west of County Road 628 - Bridge replacement is under way. The bridge is closed to traffic through early April. Motorists are advised to find an alternate route around the construction. This project is part of the Safe & Sound Bridge Improvement Program.

Miller County

• U.S. 54 bridge over the Osage River east of Lake Ozark - Bridge maintenance will take place Monday and Tuesday. One lane will be open to traffic in the work area.

• Missouri 17 between Missouri 52 and Route K - Roadway maintenance will take place Monday through Friday. One lane will be open, and crews will flag traffic through the work area.

• Route Z between Route W and Route Y - Culvert pipe replacement in various locations will take place Monday through Thursday, March 29. One lane will be open, and crews will flag traffic through the work area.

Morgan County

• Missouri 135 between Missouri 52 and Route JJ - Roadway maintenance will take place Monday through Friday, March 30. One lane will be open, and crews will flag traffic through the work area.

Osage County

• Missouri 133 bridge over Sugar Creek in Meta - Bridge replacement is under way. The bridge is closed to traffic through late April. Motorists are advised to find an alternate route around the construction. This project is part of the Safe & Sound Bridge Improvement Program.

• Route K bridge over Doolings Creek south of Chamois - Bridge replacement is under way. The bridge is closed to traffic through late April. Motorists are advised to find an alternate route around the construction. This project is part of the Safe & Sound Bridge Improvement Program.