Mid-Missouri road work for May 13-19

The following is the Missouri Department of Transportation's listing of general highway maintenance and construction work in the Mid-Missouri area through May 24.

Cole County

Route C between U.S. 54 and Missouri 52 in Morgan County - Guardrail installation, milling and resurfacing continue. Milling work will take place between Jefferson City and Russellville this week. One lane will be open, and crews will flag traffic.

U.S. 54 between the Callaway and Miller county lines - Rock cut cleaning along the eastbound and westbound lanes will take place Monday through May 24. One eastbound lane and one westbound lane will be open.

Route H over Bois Brule Creek, south of Corvette Lane - Bridge maintenance will take place Tuesday. One lane will be open, and crews will flag traffic.

Boone County

Missouri 124 over Grindstone Creek, west of U.S. 63 - New bridge construction continues. Grading and excavation, clearing and new roadway construction will take place this week. The work is not expected to impact traffic. The project is scheduled for completion in December.

Providence Road between I-70 and Route K - Signal upgrades, sidewalk repair and ADA improvements in various locations continue. Occasional lane closures are possible. The project is scheduled for completion in November.

U.S. 63 between Missouri 763 and the Randolph County line - Pavement repair continues. Work at the Missouri 22 interchange will result in periodic northbound and southbound ramp closures at the interchange. Guardrail upgrades will take place this week. One northbound lane and one southbound lane will be open. The work is scheduled for completion in November.

College Avenue between Stadium Boulevard and Rollins Street - Pavement repair continues. One lane will be open. The project is scheduled for completion in November.

Missouri 163 between routes H and K - Roadway resurfacing and shoulder widening continue. Following weather delays, shoulder widening between Route K and Tom Bass Road is scheduled to begin this week. One lane will be open, and crews will flag traffic. Sign relocations will take place along the entire project this week. The entire project is scheduled for completion in November.

Callaway County

Business 54 between the Route H and U.S. 54 interchange - Pavement improvements continue. Striping op. through the work area.

Route O between Route D and State Street - Resurfacing, shoulder additions and ADA improvements are underway. Grading operations will continue this week. One lane will be open, and crews will flag traffic.

Route O over Auxvasse Creek, east of County Road 111 - Bridge maintenance will take place Monday through May 23. One lane will be open, and crews will flag traffic.

Camden County

Missouri 242 between U.S. 54 and the Miller County line - Roadway resurfacing and shoulder widening are underway. One lane will be open, and crews will flag traffic.

Route MM between Missouri 242 and Route TT - Roadway resurfacing and shoulder widening are underway. One lane will be open, and crews will flag traffic.

Route KK between Osage Beach Parkway and Turkey Bend Road - Roadway resurfacing and shoulder widening are underway. One lane will be open, and crews will flag traffic.

Business 54 between Missouri 242 and Route MM - Roadway resurfacing and shoulder widening are underway. One lane will be open, and crews will flag traffic.

Maries County

U.S. 63 between Missouri 68 and I-44 in Phelps County - Grading, resurfacing, guardrail and rumble strip installation continue. Shoulder work and northbound acceleration lane construction continue at the intersection of Missouri 68. One lane will be open, and crews will flag traffic. The project is scheduled for completion in November.

U.S. 63 between Missouri 42 and Route AA - Roadside maintenance will take place Monday through May 23. One lane will be open, and crews will flag traffic.

U.S. 63 between county roads 325 and 341 - Rock cut cleaning will take place Monday through May 23. One lane will be open, and crews will flag traffic.

Miller County

U.S. 54 over Business 54 in Eldon - Bridge rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open. The project is scheduled for completion in mid-May.

U.S. 54 over Old Tuscumbia Road, east of Missouri 52 - Bridge rehabilitation in the eastbound and westbound lanes continues. One eastbound lane and one westbound lane will be open. The project is scheduled for completion in mid-May.

Moniteau County

Route E over North Moreau Creek, south of U.S. 50 - Bridge deck replacement continues. The road is closed during the work. The project is scheduled for completion in mid-June.

Missouri 87 between U.S. 50 and Route J in Cooper County - Pavement repair will take place May 20-23. One lane will be open, and crews will flag traffic.

Route C between U.S. 54 in Cole County and Missouri 52 in Morgan County - Guardrail installation, milling and resurfacing continue. Milling work will take place between Jefferson City and Russellville this week. One lane will be open, and crews will flag traffic.

Route KK between Route D and Gooseberry Hollow Road - Culvert pipe replacement will take place Monday through Thursday. One lane will be open, and crews will flag traffic.

Morgan County

Missouri 5 between Missouri 52 and Zulaue Street - Roadside maintenance will take place Monday through Thursday. One lane will be open, and crews will flag traffic.

Missouri 52 between Missouri 5 and Westview Drive - Roadside maintenance will take place Monday and Tuesday. One lane will be open, and crews will flag traffic.

Route C between Missouri 52 and U.S. 54 in Cole County - Guardrail installation, milling and resurfacing continue. Milling work will take place between Jefferson City and Russellville this week. One lane will be open, and crews will flag traffic.